In great British tradition, we shall start with a generic weather related comment, it's getting warmer! This has made the workshop more pleasant if nothing else, with lots as usual to report on!

Great Eastern Railway 1899 4 Wheel Brake Third 853


The roof is currently on hold as the late winter weather has meant that the roofing compound is taking its time somewhat to dry, so the order of the day has been to be busy with other tasks whilst allowing the roof to absorb as many degrees as possible. One of these tasks has been the steaming and clamping of two roof hoop shaped sections of ash that are destined for the ends of the coach pinning the edge canvas to the body. Whilst they successfully steamed and were clamped to a tighter radius than required in their finished shape, when un-clamped they sprung back to a straighter shape than desired. They have now been further adjusted and will hopefully be suitable for use next week.


Also on the outside of the coach, some of the guards handrails are being fitted to the doorways.


On the guards end of the vehicle, the end steps are now bolted on permanently and a particularly attractive feature, the red tail light, also put into position. The lighting itself needs finishing, but the physical housing is now in and can be suitably modeled if someone shines a torch through it from the inside!


Inside the guards van itself, the vacuum piping is now fully finished with a painted emergency brake valve and a very polished vacuum gauge in position in the correct places.


British Railways 1959 Brake Corridor Composite E21224


We have been able to reallocate resources onto this coach that had previously been "stolen" for the big push on M4372! This week saw recommencement of the project to renew the floors inside the side corridor and also progress on the stripping and painting of the wooden interior parts for the luggage van area. Inside the store cupboard three shelves have also been produced this week, shaped to fit (due to the curved bodyside profile of the coach, each shelf is a different length/size) and then fitted into position onto the brackets that were fitted previously.


British Railways 1955 Mark 1 Second Open M4372


The coach is being simultaneously sanded and painted, seaward and landward sides respectively. This is a cruel necessity due to the short timescale we have on this carriage, and the paint is inevitably getting dust in it as it dries! However sometimes compromise is necessary and we are progressing well with getting the coach ready to return to service as soon as possible. The seaward side paint preparation has progressed hugely over the week with large areas of the upper section (around the windows) now filled and sanded smooth.


Meanwhile, the landward side is transformed, with a coat of primer and undercoat both applied during the week. The undercoats are split as red and cream undercoats are required for the differing colours that form the "Crimson & Cream" livery. By close of play, the upper (cream) sections had also received their first coat of gloss. It is starting to look like a dining coach once again!


British Railways 1959 Tourist Second Open M4843


The final section of welding repair has now been completed to the Sheringham corridor end, bringing to and end quite a saga that was hugely more involved than originally anticipated! This heralds the half way point for the corridor end welding repairs. Attention will now soon be turning towards round 2, the Holt end, and with welding completed we can now also consider refitting the Sheringham end internally. No rest for the wicked!


British Railways 1958 Class 101 Railcar Driving Motor Brake Second M51192


Re-upholstery of the seating continues.

Easter Break


Sadly due to a combination of taking time off and going off on holidays, there will be no Blog update next week. However subject to me not getting impounded in Customs trying to bring back Hungarian carriage mementos home, normal service will resume in two weeks time! Viszont látásra!

16 March 2018

March News Part 3

Great Eastern Railway 1899 4 Wheel Brake Third 853


I was correct in my assumption last week that the suspicious package was the new roof canvas. The roof, duly prepared, was pasted in special roofing compound before the canvas was stretched on and pinned around the outside.




This involved a lot of ironing, a skill that I for one never knew a lot of the lads possessed and will no doubt be put to use back at home now that the cat is out the bag!


The finished canvas then had another thick layers of compound applied and it is currently drying, which is taking several days.


Meanwhile on the interior, an insert has been created that fits around the vacuum pipe where it comes up through the floor via a clearance hole. The end result is neater and will prevent drafts!


British Railways 1959 Brake Corridor Composite E21224


No progress to report.

British Railways 1955 Mark 1 Second Open M4372


Another week focusing on this repainting task. The landward side has continued to progress well, with the sanding and filling now completed. This side is now ready for painting next week.


The final task on the windows was remaking some patches which had fallen out of the windows. These patches were plugs for older cutouts in the windows which once carried brackets for roof boards. These were fitted just below the gutter for named trains such as "The Pines Express" or "The Flying Scotsman". In case anyone was suggesting reinstating the brackets, sadly they appear to be random and in the wrong places, betraying the secret that the windows on this coach are not original and have been salvaged from a scrapped classmate.

On the seaward side, the aluminium window frames are now fully stripped and sanded back to bare metal. Failed rivets have been replaced and any surface corrosion around vulnerable areas cleaned back and treated. Next week will see paint preparation work move onto this side.


All four doorways have also been prepared for repainting and any small remedial work carried out.

British Railways 1959 Tourist Second Open M4843


We are at last on the home straight for the welding repairs to the Sheringham end. Just one more section of panelwork now to fit (above the corridor connection) and that should see the major renewal completed. The corroded framework below where the new panel is destined has been cleaned and painted ready.


British Railways 1958 Class 101 Railcar Driving Motor Brake Second M51188


This has now been successfully put into traffic with our interior work to the guards van completed.


British Railways 1958 Class 101 Railcar Driving Motor Brake Second M51192


In a mass removal session, all of the remaining seat backs and side pieces were removed from the vehicle this week so that they can be reupholstered in due course.


The front saloon (behind the cab) has also been the seat frames sanded back and repainted blue in the same way as we did in January with its partner M56352. This work can only be done with the cushions removed but before the new ones start being refitted!

British Railways 1958 Class 101 Railcar Driving Trailer Second Lavatory M56352


Similar to M51188, it has now been successfully put into traffic with re-upholstery work completed. As promised last week, I have photographic evidence of the final (of the three) passenger saloons to be fully fitted out with the newly upholstered seating.

09 March 2018

March News Part 2

With the snows gone we are back to full strength with the department once more running normally, well as close to normal as we can manage given the reprobates that frequent the building!

Great Eastern Railway 1899 4 Wheel Brake Third 853


The scaffolding continues to be put to good use with any gaps or edges smoothed or sealed along the replacement plywood which has been attached to the roof. There is also a large and suspicious package that has been left unattended next to the coach (like the ones we are told to report if we see in a public place!) which we think may be the new canvas covering? All will be revealed next week when "Team Great Eastern" are back in and open it...

Inside the vehicle, the handbrake pedestal and wheel have now been fitted properly, this was possible now that the body and chassis are united again. The guard's emergency valve and associated pipework has also been fitted adjacent to the handbrake.


Another  "swan-neck" vacuum pipe has been made for the outside of the vehicle, but can't currently be fitted as the scaffolding is in the way!

British Railways 1959 Brake Corridor Composite E21224


No progress to report.

British Railways 1955 Mark 1 Second Open M4372


This coach has been the main focus of the works this week, sadly the focus has been progressing very tedious and non-newsworthy tasks. The landward side aluminium window frames are now fully stripped and carefully sanded back to bare metal. Failed rivets have been replaced and any surface corrosion around vulnerable areas cleaned back and treated. What this has allowed is the start of the filling and paint preparation sanding work to be done. So far, about a third of the side has been prepared.


Meanwhile, the seaward side (slightly behind) has been progressing simultaneously. The first job, that of burning off all of the cream bodyside paintwork, has now been completed. Phase two, stripping/sanding of the aluminium window frames, is now also well advanced. The above work would ordinarily take weeks and weeks (as it did for E21224 last year) but by putting more than half of our workforce onto this single task, it has been condensed into a much smaller timescale.


British Railways 1959 Tourist Second Open M4843


Some more panel-work, this time around the sides of the corridor, has been permanently fitted.


British Railways 1958 Class 101 Railcar Driving Motor Brake Second M51188


The railway's latest DMU (hired in) has yet to see passenger service, being booked out tomorrow (at the time of writing). Members of C&W have assisted the locomotive department to have a good stab and getting mechanical and electrical issues with it sorted before it goes into service, however that work is largely outside the remit of this Blog. Of relevance here has been the continued cosmetic attention to the guards brakevan area, which needed some loving care when it came to us. We have removed the mushrooms from in there(!) but unfortunately the wall paneling that the fungi were growing in was not salvageable, so new panels have been made, fitted and painted. The remaining walls have also been repainted to spruce up the whole area and it now looks a lot better than it was a fortnight ago. I will try and get a "completed" picture in next week.

British Railways 1958 Class 101 Railcar Driving Motor Brake Second M51192


As mentioned last week, the re-upholstery department are now progressing their next vehicle. The lower seat cushions continue to be focused on, as none of the seat backs have yet been removed from the vehicle.

British Railways 1958 Class 101 Railcar Driving Trailer Second Lavatory M56352


The final half dozen seats have now been returned to the vehicle this week, ready for the March weekend running days. This now completes this task and we can walk away from the vehicle, content in the knowledge that it is fully reupholstered and ready to take on the 2018 season! Again, I will try and get a "completed" picture in next week.

Maintenance


A final note, after a few drawhooks failing testing recently we decided to asses our spares of these and gauge them all to work out how many "duff" ones we have hidden away and how many spares we hold ready to fit when needed. Consequently the box has been emptied and tests done to determine that about 1/3rd of what's in the box are failed examples. It's useful to know these things when running a fleet of 30 coaches!

02 March 2018

March News Part 1

The snowfall this week unsurprisingly crippled the railway with the works effectively being shut down by the middle of the week. A very low turnout of staff and volunteers has obviously meant there is much less to report on this week. However members of the department were admirably in attendance every day, spending time assisting other departments to keep things going during the disruption.


Great Eastern Railway 1899 4 Wheel Brake Third 853


No progress to report.

British Railways 1959 Brake Corridor Composite E21224


No progress to report.

British Railways 1955 Mark 1 Second Open M4372


All of the cream paint on the bodyside along the landward side has now been successfully stripped off. We are now progressing the next phase of stripping which is getting the nine window frames on this side back down to bare aluminium so we can start again with them. This is very fiddly work with lots of little crevices and takes a disproportionate amount of time to do!


After they are stripped any gaps around the outsides are being sealed up and any failed rivets drilled out and replaced.


British Railways 1959 Tourist Second Open M4843


The corner of the roof has now been returned to its rightful place after a section of galvanised steel was let in.


British Railways 1958 Class 101 Railcar Driving Motor Brake Second M51188


No progress to report.

British Railways 1958 Class 101 Railcar Driving Motor Brake Second M51192


Now that the upholstery team have finished renewing the material of the National Railway Museum's trailer car (M56352), they have moved onto the other half which is currently inside the loco shed for engine repairs. So far, several lower seat cushions have been taken from the vehicle and are now being recovered.

British Railways 1958 Class 101 Railcar Driving Trailer Second Lavatory M56352


No progress to report.

24 February 2018

COMPLETION SPECIAL: Mark 1 Covered Carriage Truck E94464


Our "Completion Special" updates are normally reserved for the completion of Gold standard overhauls, however an exception is being made for E94464 as it has spent over ten years out of passenger service, and also because whilst it was originally brought in for a Bronze overhaul, most areas of the vehicle have in fact received a Silver level of work, with some even getting Gold treatment.

E94464 is one of two Covered Carriage Trucks (CCT) owned and operated by the North Norfolk Railway. It is part of the British Railways standard Mark 1 family, but is unlike most other Mark 1 variants in many ways. Weighing 17 tons, it is a short vehicle on a fixed 4-wheeled chassis and has no accommodation for passengers. Instead there is a large open area inside for any goods or parcel traffic that may be required to be stowed. Access is either through one of the four sets of double opening doors in the bodysides, or through either end of the vehicle which is equipped with wooden folding doors and a tail gate which can be hinged down over the buffers. This latter feature allowed road cars to be driven into the vehicle at one end and along a train of similar vehicles, much in the way that the Channel Tunnel shuttle services operate today.  E94464 was originally built with folding shelves along the walls, these could be stowed upwards if cars etc were being carried, or folded down to provide additional storage for smaller packages if required. These tables were later removed but it is not known if this was done in British Rail days or by NNR volunteers. Three windows each side allow light into the vehicle, with electric lighting also being fitted. E94464 is roughly in the middle of a huge production run of 923 CCT vehicles built between 1959 and 1961 at British Railway's Earlestown works, being supplied to the Midland, Eastern and Western regions. Many were later transferred to the Southern region, with only the Scottish region having nothing to do with them. As the prefix to the number suggests, E94464 was one of 120 CCT's originally built for the Eastern region.

E94464 rolled off the production line in 1960 finished in lined out British Railway's maroon livery. being the tenth CCT delivered to the Eastern region. It was immediately put to work operating mixed goods and parcels trains as required. It's vacuum braking system and comparability with passenger stock would have also allowed the vehicle to be attached to passenger trains as well to provide extra goods accommodation. We have no records of E94464's exact allocations or travels, but there is no doubt it would have toured the country in the course of its duties. During the late 1960's/early 1970's, E94464 was repainted into BR's new corporate blue livery, losing its lining in the process.

A few odd CCT vehicles were taken out of service in the 1970's, however the 1980's were to prove disastrous for the type. From 1981 onwards, CCT's were withdrawn in their hundreds, with only a handful surviving beyond 1985. The last vehicle remaining was recorded as being withdrawn in October 1989. E94464 was one of the earlier casualties, being taken out of use in April 1981. The reasons for withdrawal en-masse are thought to be a general decline in parcel traffic on the railways and an increasing move away from older designs of stock with 4-wheeled chassis and vacuum brakes.

E94464 was not to rest for long however, being purchased by the North Norfolk Railway later that year (1981) and transported to Sheringham to begin a new life in "working retirement". CCT's were useful as multi purpose vehicles on growing heritage railways, the NNR being no exception, and E94464 was useful as both a stores van and workshop area. A whopping 74 CCT's were transferred into preservation in total! In the 1990's the vehicle was semi-permanently attached to one end of the Carriage & Wagon tent at Weybourne, and the remains of the brackets on the end of the vehicle remain to this day as a small reminder as to its previous occupation.


By the time of the early 2000's, E94464 had been in NNR ownership for the same number of years than it had been BR. This period was also to see E94464's return to regular service. A new cycling initiative was being pursued by the railway, and two CCT vehicles were attached to the Sheringham ends of the two main summer service sets of Mark 1 vehicles. However resources were limited and E94464 had deteriorated during its time as a static store. It was quickly revived and repainted into a plan (unlined) maroon colour and put into service. E94464 then operated for approximately five years running every day there was two Mark 1 sets in service, carrying bicycles and buggies as required.


Further deterioration to the doors and running gear led to E94464 being withdrawn from service once again in the mid 2000's (its place being taken by suburban brake E43357) and it was stored at Sheringham where it was used again as a store for the commercial/events department.


The vehicle lay at Sheringham for the best part of ten years until a change of circumstances brought it "back into the fold". The catalyst was the Suburban 4 project which saw four of the railway's suburbans restored to a high standard and removed from normal services to be formed as a special set in their own right. This resulted in suburban brake E43357 being lost from the main service trains, leaving the railway short of a bike carrying vehicle. As a short term measure, the M&GN Society's "Fruit D" goods van was borrowed to serve as a replacement, however after two summers it became apparent that the level of use was proving unsuitable to the wooden bodied Fruit D. A replacement was needed urgently. Early suggestions included securing another CCT from a heritage railway, however given the level of work required on a new vehicle to make it suitable for passenger services, it was decided that E94464 was the best option as it was a (reasonably) known quantity.

Brought into the workshops in July 2017, the underneath required lubrication, springing adjustment and repainting. The body was to prove much more troublesome, with terminal corrosion present in much of the vehicle. There were riveted patches all over it, and unable to dedicate too much labour to it, we had to make a decision what was to be tackled and what was to be re-patched. It was decided to keep all of the patches along the bottom edge of the vehicle, with everything above that being repaired. This included the complete rebuilding of all six of the window bottoms which had completely wasted away through window leaks over the years.


We returned all of the original features to the bodysides, including the prominent wooden destination chalk boards, such a feature of these vehicles. The wooden end doors had rotted badly so were fully rebuilt and partially replaced. They were also made to work again so it would now technically be possible to drive vintage cars once again into the vehicle! A full repaint, for the first time back into as-built fully lined and lettered maroon livery, finished off the outside.


The inside was sanded down, repaired where required and repainted into original freight brown colours. The ceiling had badly bowed with water damage so had to be teared down and completely replaced. The floor was de-pot-holed and also repainted.


February 2018, seven months after the start of the project, saw E94464 released back into service. It is hoped that this vehicle can join the main set (or "A set") of coaches which generally sees service seven days a week and which is enjoyed by the vast majority of our visitors.


Great Eastern Railway 1899 4 Wheel Brake Third 853


Sticking with 4-wheeled vehicles, the dramatic transformation of 853 featured last week has continued at a similar pace, with scaffolding being erected around the coach to allow roof work to be tackled.


Up top, the original roof, de-canvassed revealing the original boards below, was vacuumed off leaving a surface on which to work on. Thin plywood panels have been nailed onto the original roof to smoothen out all of the discrepancies, sharp edges and other age-related issues. This creates a better surface for the replacement canvas covering to be bedded down onto.


Other smaller fittings are also being progressed, by those who have no appetite for heights! These have included the fitting of the second emergency chain to the Holt end bufferbeam (used in times gone by in case the main coupling snapped). The upper foot board steps have also been bolted on permanently and are currently in undercoat.

British Railways 1959 Brake Corridor Composite E21224


Progress on all of the fronts discussed last week. Firstly, all of the areas of bare metal are now primed to offer it limited protection for when the coach goes to Bridge Road sheds later this year.


Secondly the store cupboard has moved onto the next coat of paint, a fetching pink primer!


Lastly the flooring repairs are continuing along the corridor now that the compartments are completed. Several replacement square sections have been produced and gloss painted on the backs to protect them once they are finally fitted.

British Railways 1955 Mark 1 Second Open M4372


The release of E94464 of course means we have a new project! 4372 is part of the dining train and is generally in very good condition. Unfortunately the cream paint used on the bodysides has crazed and broken down badly since it has been in service leading to deterioration and unsightly rust streaks. Whilst the underframe and interior require no work whatsoever, the exterior now requires repainting.


Irritatingly the reacted paint means that the cream will need stripping off fully which has been the first task, started this week. Several window fixings have failed so they are going to require stripping, resealing and re-securing. There is a lot of work to do on 4372 and very little time to do it in, so resources are being concentrated intensely in order to complete this one faster. It will be interesting to see over the coming weeks how fast we can move this one forwards using this approach.


British Railways 1959 Tourist Second Open M4843


The end is starting to be in sight for the Sheringham end seaward side corner. Panelwork is now being welded into position, with several complicated corner sections being tackled this week.


British Railways 1958 Class 101 Railcar Driving Motor Brake Second M51188


The railway has hired a Class 101 DMU powercar for the 2018 season to cover for the National Railway Museum (which suffered an engine failure earlier this month) and NNR (overhaul not yet completed) vehicles. It is to be used on services as soon as possible however there are several features which do not meet our service standards. This has included several doors which do not open/shut properly, although hopefully these can be solved with replacement of minor items within the hinges etc. These repairs have been started this week and can hopefully be completed in a couple of days. Other fun discoveries included mushrooms growing in the guards compartment! There is a great deal of damp in this area and two panels have had to be removed as they broke apart when prodded. These are being replaced with new examples.

British Railways 1958 Class 101 Railcar Driving Trailer Second Lavatory M56352


No progress to report.

Southern Railway 1939 Parcels & Miscellaneous Van S1359S


This van was moved from Weybourne to Sheringham at the same time as CCT E94464, so is now officially released from our workshop!


Maintenance


Amazingly, what with all of the other action going on, routine maintenance work has been able to continue. Some of the faults flagged up during C examinations at Sheringham are being tackled. A rotten ceiling from Corridor Second E25189 has been ripped down and a replacement made in the workshop, which is currently being painted. Meanwhile, an overhauled buckeye coupling has been fitted to dining car E1969 after its original was found to be worn.

17 February 2018

February News Part 3

Great Eastern Railway 1899 4 Wheel Brake Third 853


The headline news this week has to be the unification of the body and underframe following 11 months work rebuilding the running gear. The body was carefully jacked up and the completed underframe then rolled underneath. The body was then lowered slightly and carefully aligned onto the rubber pads which sit between the steel chassis and the framework of the body. The following day was spent bolting down the body which pulled it into a flat position, as it had settled to become slightly banana shaped whilst it was a grounded body. It is remarkable to note that this body now has wheels for the first time in 91 years! Quite an achievement for those involved...



British Railways 1959 Brake Corridor Composite E21224


The exterior paint preparation has been completed along the side of the brake/luggage compartment on the seaward side. This is now ready for painting, which will have to be done before the coach goes "on holiday" to Bridge Road sheds whilst the workshops are taken over by the Quad Arts later this year.

Internally, the floor repairs to the second compartment which needed them have been completed, so we now have a full compliment of five compartments with no rotten flooring! The store cupboard has received its first coat of paint, a special primer which is designed to key onto smooth surfaces such as Formica.

British Railways 1959 Tourist Second Open M4843


More metalwork has been completed on the Sheringham corridor end. A start has also been made on removing some of the apparatus on the Holt end corridor ready for welding repairs to start on that end in due course.

British Railways 1958 Class 101 Railcar Driving Trailer Second Lavatory M56352


No progress this week as the vehicle has been in use on February half term services!

British Railways 1960 Covered Carriage Truck E94464



We are nearly there with this one... Signwriting continues on the exterior, there is such a lot of it on this particular vehicle! The black part of the middle (waist height) line has also been applied.


The underframe has received a coat of black gloss finishing it off, and several smaller items have been picked out, including white handbrake handles and red battery charging sockets. Other lettering such as the white stars on the underframe (which show where the brake release chords are located) have also been added. The final underframe task, brake testing, is now in progress and we are currently repairing the several leaks that were found. The steel vacuum pipe had rotted away at the Sheringham end, and various rubber hoses also require changing.


On the inside, the Sheringham end folding doors are now painted in brown to match the rest of the walls, meaning there is now no more work to be done on the side walls. The floor has also received two coats of red floor paint which has transformed its appearance.


The last job now remaining on the interior is to paint the wooden floor boards in the four doorways and then it shall be complete.

Southern Railway 1939 Parcels & Miscellaneous Van S1359S


This has now been out-shopped, but I have yet to get the chance to capture a decent picture of it!

Other Projects